“Locker cover-up” project is starting on Main Building 2nd & 3rd floors
Work is underway in July to cover up lockers on the second and third floors of the Main Building with painted drywall. This work is a continuation of locker cover-up projects already completed in other portions of the Main Building.
Students and employees with items in the affected lockers have until end of day on Thursday, July 11, to remove their possessions. Signs have been posted to let the locker users know.
- On Friday, July 12, if necessary, locks will be cut and materials removed from the affected lockers.
- Materials removed from lockers can be claimed by calling Campus Police at (513) 569-1558.
Areas of the Main Building affected are:
- Section 1 – Second floor hallway from Main to ATLC
- Section 2 – Second floor hallway from Main to Health Professions Bldg.
- Section 3 – Third floor hallway areas between the Business Division Office and the Conference Center
- Section 4 – Third floor hallway from Main to Health Professions Bldg.
Prep work for the project begins Monday, July 8, in hallway ceilings adjacent to the affected lockers. Contractors involved with the project will be working from 6 a.m. to 2 p.m. daily.